10MW Solar Farm, Gebeng 2014

10MW Solar Farm, Gebeng 2014

Production of 10MW power output consists of staggering 33,336 pieces of 300W solar panel installed on aluminium structure.

With 4 phases involved, each phase solely generated approximately 2.5MW assisted by 4 inverters rated 630W each.

Not to forget, 20 array junction boxes (AJB) are connected parallel with each other before linking them up with installed inverters.

Subsequently, 1300kVA transformers are fed the output power by inverters for voltage stepping-up purpose in order to feed into nearest 11kV sub-station before connecting to the national grid.

A number of 4 months required to accomplish half portion of the farm, particularly phase 1 and 2, after commencing on September 2013.

Various sizes of DC cable are utilized for connecting every group of 18 solar panels called string to AJB just to meet the current carrying capacity and voltage drop requirement.

Additionally, each phase particularly carrying 2.5MW output power, with the aid of high tension (HT) specialist as Times-Lite often deal with, completed the HT cable laying to feed the power up to newly-constructed Main Switch Station (Stesen Suis Utama, SSU).

As for cable termination and all other HT stuff in switchgear room, Times-Lite also possesses specialists to make sure the completion a success.

Farm successfully completed in its quite rapid and hard construction time and the testing and commissioning came by on May 2014 for the next phase 3 and 4.

As to mention, Times-Lite often never left behind in testing and commissioning scope in which we possesses competent person to handle the job. Testing and calibrating mostly all electrical equipment on site is solely done by us to ensure the efficient and effectiveness of those equipment.

Testing and commissioning of AC and DC perform by Times-Lite as well as we have the specialists and tools to get the job done. Alternate current (AC) testing comprising low voltage (LV), extra low voltage (ELV) and mechanical and electrical (M&E) testing.

In M&E, Times-Lite deal with lot of job scopes that comprises the installation of the likes of inverter ventilation, firefighting and air-conditioning system.

The crucial part is handling the completion of high tension (HT) and it’s testing and commissioning surely needs reliable person to ensure the system is running as it is supposed to be.

However the solution is easy-gain in which Times-Lite independently has its own competent person, providing the best services as we own certified skills.